Good buyer. Buyer profile is in relatively good shape. The competition for contracts is high.
Is the level of competition satisfactory? detailed info
|
Largest contracts Industry |
Bids |
|---|---|
|
Odkanalizování místních částí Vlčovice a Mniší
Sewage, refuse, cleaning and environmental services |
7
Ø2 in industry |
|
Revitalizace centra města Kopřivnice III
Construction work |
4
Ø4 in industry |
|
Stavební úpravy domu s pečovatelskou službou - Masarykovo náměstí 650/11, Kopřivnice
Construction work |
4
Ø4 in industry |
|
Úprava veřejných prostranství, příjezdová komunikace a parkovací plochy v okolí nového Technického muzea v Kopřivnici - 1. etapa
Construction work |
6
Ø4 in industry |
|
„Rekonstrukce TZB v objektech města Kopřivnice“
Construction work |
4
Ø4 in industry |
Isn't majority of contracts awarded to small circle of firms? detailed info
| Largest suppliers | Contracts count | Contracts volume Kč |
|---|---|---|
|
STASPO, spol. s r.o. |
1 | 119,340,074 |
|
GEOSAN GROUP a.s. |
1 | 98,488,900 |
|
THERM, spol. s r.o. |
5 | 47,337,813 |
|
HAMROZI s.r.o. |
2 | 28,025,746 |
|
STRABAG a.s. |
1 | 27,407,046 |
| Other suppliers | 154 | 465,959,915 |
| Supplier | Contracts count | Contracts volume (Kč) |
|---|---|---|
|
STASPO, spol. s r.o. |
1 | 119,340,074 |
|
GEOSAN GROUP a.s. |
1 | 98,488,900 |
|
THERM, spol. s r.o. |
5 | 47,337,813 |
|
HAMROZI s.r.o. |
2 | 28,025,746 |
|
STRABAG a.s. |
1 | 27,407,046 |
|
NH stavby s.r.o. |
8 | 26,356,166 |
|
STAVEBNÍ SPOLEČNOST ŠURÍK s.r.o. |
2 | 17,122,957 |
|
CHALUPA A SYN, s.r.o. |
8 | 16,854,801 |
|
SWIETELSKY stavební s.r.o. |
5 | 12,420,143 |
|
STAVBY A STATIKA spol. s r.o. |
3 | 8,720,126 |
|
T-Mobile Czech Republic a.s. |
1 | 8,560,628 |
|
Severomoravské vodovody a kanalizace Ostrava a.s. |
1 | 8,296,832 |
|
V+V SAVEKO s.r.o. |
4 | 6,472,020 |
|
Severomoravská stavební společnost s. r. o. |
1 | 5,606,980 |
|
Art Consultancy s.r.o. |
1 | 5,479,115 |
|
SLUMEKO, s.r.o. |
7 | 5,003,645 |
|
JAPSTAV MORAVA s.r.o. |
4 | 3,509,305 |
|
INGDOP s.r.o. |
1 | 3,332,859 |
|
MERAT s.r.o. |
1 | 2,977,777 |
|
Jindřich Lukeš |
11 | 2,900,448 |
|
DEV COMPANY, spol. s r. o. |
1 | 2,593,489 |
|
Zdeněk Hybner |
1 | 2,468,322 |
|
PELA CZ, a.s. |
12 | 2,222,027 |
|
KÁMENBAU s.r.o. |
1 | 1,957,913 |
|
JVAgro Morava s.r.o. |
1 | 1,893,141 |
|
SEMITA - DS s.r.o. |
1 | 1,849,088 |
|
ČECH - ENGINEERING, a.s. |
2 | 1,834,000 |
|
VERA, spol. s r.o. |
1 | 1,779,040 |
|
COLAS CZ, a.s. |
1 | 1,773,383 |
|
FLAME System s.r.o. |
2 | 1,200,050 |
|
Petr Štěpán |
8 | 1,054,387 |
|
Výtahy-Elektro Žižka spol. s r.o. |
1 | 1,044,000 |
|
Aleš Kopčák |
1 | 968,105 |
|
Michaela Kurcová |
2 | 870,341 |
|
Tomáš Kadlec |
4 | 822,970 |
|
Vítězslav Štencel |
1 | 782,618 |
|
KOMTERM Čechy, s.r.o. |
1 | 768,170 |
|
ELKOPLAST CZ, s.r.o. |
1 | 750,000 |
|
STAVIA - silniční stavby, a.s. |
1 | 659,824 |
|
ENERGO-STEEL spol. s r.o. |
2 | 617,833 |
|
Sun Drive s.r.o. |
1 | 586,320 |
|
WALFER spol. s r. o. |
1 | 504,500 |
|
AGROTEC a.s. |
1 | 495,389 |
|
TERRA - POZEMKOVÉ ÚPRAVY, s.r.o. |
1 | 485,000 |
|
UNISTAD spol. s r. o. |
1 | 484,828 |
|
Rušar mosty, s.r.o. |
1 | 480,000 |
|
Mostní vývoj, s.r.o. |
1 | 470,900 |
|
Martin Urban |
1 | 464,746 |
|
RELY servis s.r.o. |
1 | 454,537 |
|
INTERNOVA MORAVA s.r.o. |
2 | 446,299 |
|
RON Software, spol. s r.o. |
1 | 421,448 |
|
Hybaj s.r.o. |
1 | 411,862 |
|
M2AU s.r.o. |
1 | 408,000 |
|
Ing. Dagmar Krestová - VÁGNER výroba nábytku |
1 | 398,000 |
|
PEGASUS Service s.r.o. |
1 | 390,668 |
|
Hasičská vzájemná pojišťovna, a.s. |
1 | 367,332 |
|
Global Payments s.r.o. |
1 | 360,000 |
|
ESO R-MARKET spol. s r.o. |
1 | 308,826 |
|
Aktiv Novostav, s.r.o. |
3 | 296,574 |
|
Ladislav Rýpar |
3 | 284,224 |
|
KONSTRUKTIAL s.r.o. |
1 | 276,421 |
|
Ing. Lukáš Štefl |
1 | 259,995 |
|
MARK VALA s.r.o. |
1 | 243,000 |
|
LEGOLA CZECH s.r.o. |
1 | 199,900 |
|
RAUERHOLZ s.r.o. |
1 | 181,023 |
|
Zich a spol., s.r.o. |
1 | 180,000 |
|
vegler s.r.o. |
1 | 169,000 |
|
Kubinová + partneři, s.r.o. |
1 | 164,000 |
|
HaskoningDHV Czech Republic, spol. s r.o. |
1 | 157,300 |
|
STAREST s.r.o. |
1 | 127,800 |
|
AutoCont CZ a.s. |
1 | 94,900 |
|
Havířovská inženýrská kancelář, spol. s r.o. |
2 | 91,000 |
|
ENELA stavební s.r.o. |
1 | 82,000 |
|
SAFETY PRO s.r.o. |
1 | 64,000 |
|
JC Forestgang s.r.o. |
1 | 62,985 |
|
ALWIL Trade, spol. s r.o. |
1 | 60,000 |
|
ZAKÁZKY.EU s.r.o. |
1 | 58,900 |
|
Scenario s.r.o. |
2 | 58,780 |
|
COMP`S, spol. s r.o. |
1 | 58,480 |
|
CS21 Nextnet, s.r.o. |
1 | 30,578 |
|
Centrum dopravního výzkumu, v.v.i. |
1 | 28,900 |
|
FLAGRO a.s. |
1 | 18,500 |
Does the buyer foster the competition by using the available tools? detailed info
| Tool | Contracts count |
|---|---|
| Extended deadlines | 11% (1 from 9) |
| Nonprice competition | 17% (4 from 24) |
| Division into lots | 8% (2 from 24) |
| E-auction and DPS | 0% (0 from 24) |
| Innovative procedure | 0% (0 from 24) |
What fraction of purchases was made under procurement law? detailed info
| Purchases | Volume (Kč) |
|---|---|
| Public procurement | 560,384,743 |
| Small scale tenders | 154,307,208 |
| Unregulated purchases | 606,976,074 |
| Total | 1,321,668,025 |
| Budget item | Objem prostredku Kč |
|---|---|
| Durable property purchases | 605,624,889 |
| Material consumption | 24,551,376 |
| Energy consumption | 36,250,800 |
| Other consumption | 430,015 |
| Sold goods | 107,849 |
| Activation of durable property | 0 |
| Activation of consumable property | 0 |
| Change of stock | 0 |
| Maintenance and repairs | 373,615,654 |
| Travel costs | 1,562,176 |
| Representation costs | 2,070,281 |
| In-house services | 0 |
| Other services | 252,675,265 |
| Small long-term property costs | 15,534,533 |
| Other costs | 9,245,187 |
Did buyer violate law significantly? detailed info
| Name | Misconduct |
|---|---|
| Revitalizace centra města Kopřivnice | NO |
| Revitalizace centra města Kopřivnice | NO |
How often does buyer use non-competitive procedures? detailed info
|
Contract Reason for negotiated procedure without publication |
Original contract (Kč) | Contract modification / NPWP (Kč) |
|---|---|---|
|
Přeložka stávajícího vodovodního řadu v Kopřivnici, místní část Mniší vyvolaná stavbou kanalizace Authorship rights |
- | 8,296,832 |
|
Odkanalizování místních částí Vlčovice a Mniší Contract modification |
119,340,074 | 4,642,329 (+4%) |
|
Stavební úpravy domu s pečovatelskou službou - Masarykovo náměstí 650/11, Kopřivnice Contract modification |
28,430,174 | 2,237,042 (+8%) |
|
Úprava veřejných prostranství, příjezdová komunikace a parkovací plochy v okolí nového Technického muzea v Kopřivnici - 1. etapa Contract modification |
27,407,046 | 1,989,570 (+8%) |
|
DDM Kopřivnice - rekonstrukce sociálních zařízení včetně bezbariérové úpravy, elektroinstalace a rozvodů TZB Contract modification |
8,010,185 | 735,147 (+10%) |
Does buyer discourage bidders by frequent competition cancellations or modifications? detailed info
| Type of flaw | Result |
|---|---|
| Issued tenders without published result | 0% |
| Cancelled contracts | 38% |
| Average requirements modifications count | 1.00 |
| Average decision length | 79.25 days |
| Contract | Modifications count | Cancelled | Without results | Decision length |
|---|---|---|---|---|
| Realizace muzejní expozice Dany a Emila Zátopkových II | 0 | 23 | ||
| Revitalizace centra města Kopřivnice | 0 | 140 | ||
| Odkanalizování místních částí Vlčovice a Mniší | 3 | 69 | ||
| Realizace muzejní expozice Dany a Emila Zátopkových | 0 | 27 | ||
| Odkanalizování místních částí Vlčovice a Mniší: činnosti TDI a koordinátora BOZP | 0 | 67 | ||
| Revitalizace centra města Kopřivnice II | 3 | 125 | ||
| ZŠ Alšova - vybavení kuchyně | 0 | 72 | ||
| Revitalizace centra města Kopřivnice III | 2 | 111 |
Does buyer publish vital data in official journal? detailed info
| Type of flaw | Contracts count |
|---|---|
| Bidders count not published | 0% (0 from 25) |
| Procedure type not published | 0% (0 from 25) |
| Missing buyer ID | 0% (0 from 25) |
| Missing call for tenders | 0% (0 from 25) |
| Missing winning price | 0% (0 from 25) |
| Contract modification by more than 50 % | 0% (0 from 25) |
Does the buyer profile fulfill the legal requirements? detailed info
| Is the buyers website consistent with central procurement registry? | 92% (zakázek z 24 ve Věstníku) | ||||||||||||
| Are there obvious flaws or inconsistencies within the data? | 0.38 (average mistakes per contract) | ||||||||||||
| Are small scale tenders published on a buyer profile? (Compared to quantity of 24 tenders under the law) |
|
| Contract | Type of discrepancy |
|---|---|
| Kulturní dům Kopřivnice - rekonstrukce střešních plášťů | Tender not found on any profile |
| Revitalizace centra města Kopřivnice - zajištění činnosti technického dozoru stavby a koordinátora BOZP - II. | Payment information missing |
| Kulturní dům Kopřivnice - rekonstrukce střešního pláště | Tender not found on any profile |
| Odkanalizování místních částí Vlčovice a Mniší | Payment information missing |
| Odkanalizování místních částí Vlčovice a Mniší: činnosti TDI a koordinátora BOZP | Payment information missing |
| Telekomunikační mobilní služby pro město Kopřivnice a jiné veřejné zadavatele | Payment information missing |
| Bytové domy č.p. 1111-1113 na ulici Horní v Kopřivnici - snížení energetické náročnosti | Payment information missing |
| DDM Kopřivnice - rekonstrukce sociálních zařízení včetně bezbariérové úpravy, elektroinstalace a rozvodů TZB | Bid evaluation protocol missing |
| Revitalizace centra města Kopřivnice III | Payment information missing |
Have the tenders according to companies been procured fairly and professionally? detailed info
Buyer did not get enough feedback (yet) to get a statistically relevant rating from his tender participants. Thus he gets standard rank of 80 %.